Friday, July 21, 2017

Not Quite Ready: Lambert Lane Construction Continues

"Update on road construction at Lambert Lane & La Cañada Drive

Oro Valley, Arizona (July 17, 2017) – Although Lambert Lane re-opened to drivers on June 30, there is still a tremendous amount of work being performed at the Lambert & La Cañada intersection, and motorists should continue to exercise caution and vigilance when driving through this area. Once completed, this section of Lambert Lane, west to Hacienda Hermosa, will be four lanes wide with a left-turn lane and a right-turn lane in each direction, plus a bus pullout on southbound La Cañada and another pullout on eastbound Lambert. The project is slated for completion later this year.

WORK COMPLETED SO FAR

So far, crews have performed critical infrastructure work, including adjustment and installation of utilities, and grading and moving more than 60,000 cubic yards of soil to widen the roadway and reduce the height of the hill to improve safety and visibility. Extensive slope stabilization work has been performed on both sides of the streets via construction of soil nail walls. New traffic signals have been installed, and old ones have been removed. Some of the paving work has been completed, and work has begun on erosion control materials and stormwater control measures, with the installation of storm drain pipe and catch basins.

WORK THAT WILL BE PERFORMED OVER THE NEXT FEW MONTHS

In the coming months, as crews wrap up the final stages of road paving and curb installation, new striping and signage will follow. They’ll also complete some of the major safety features, such as the installation of a concrete sidewalk on the north side of Lambert, and the construction of a 10-foot-wide, multi-use path on the south side of the road. Stormwater efforts will continue, with the placement of a storm channel on the north side of Lambert. Residents and motorists will also notice some aesthetic enhancements, as architectural treatments are applied to the soil nail walls, and decorative rock and metal cacti are installed throughout the project. Lastly, native vegetation will be replanted (along with the installation of new irrigation lines).

HOW TO STAY INFORMED

There are three great ways to learn more about this project and stay informed about future updates: · Check out the project photo album on Facebook. (You do not need to have a Facebook account to view the pictures).


UPCOMING LANE RESTRICTIONS

The Town of Oro Valley is grateful for the community’s patience and safe driving during this time. Please be mindful of ongoing work in the area and traffic control measures such as barricades and reduced speeds. The Town will issue “Traffic Alerts” when significant lane restrictions will be put into place, impacting your daily drive.

Two such alerts include the following (dates subject to weather): ·

  •  7/24/17—7/28/17: Lane restrictions on northbound and southbound La Cañada at Lambert for median curb removal, grading, new curb construction and backfill.
  •  8/4/17—8/7/17: Severe lane restrictions in all directions for median grading and paving.

PROJECT BACKGROUND

The Lambert Lane Phase II Project was launched to improve safety and visibility along Lambert, while widening the roadway to accommodate additional travel lanes, multi-modal enhancements, curbs and landscaping. The work is being performed by Granite Construction, Inc., and the project is funded by the Pima Association of Governments."

(Source: Town Of Oro Valley Press Release)